Original Article: Kylie Knight, Moreton Daily, “Work to start on landmark development,” published 31 March 2025 at 5:03am.

Gardner Vaughan’s One Redcliffe development will bring the biggest change to the Redcliffe foreshore in more than a decade when the landmark project is completed in 2029.

Commercial Director Sam Gardner sat down with The Redcliffe Peninsula to talk about the project he says will be more than just a development.

One Redcliffe will be built in two stages, delivering 214 apartments across two towers and 12 ground-floor retail and commercial spaces.

It will also feature a resort-style lifestyle precinct with two outdoor swimming pools, gymnasium, and barbecue facilities.

Work will start on stage one from mid-year, with the large site at the corner of Anzac Ave and Redcliffe Pde, to be cleared of existing structures before then.

“The idea is the first tower will take 27 months from mid-year to quarter three or quarter four of 2027. The second stage of the development will be around 18 months after that,” Sam explains.

“As the structural team finishes the first tower, they will then move into stage two. There will be an overlap.

“We wouldn’t do them together purely based on the scale … there’s a lot of risk in that for our business. We’re also cognisant of the fact there are people living next to a construction site.”

Sam says the team will manage the project to mitigate dust and noise, and will keep the community informed along the way.

One Redcliffe is Gardner Vaughan first development on the Redcliffe Peninsula but is likely to be the first of many.

“We have had our eyes on Redcliffe and we love to see how far it’s come. (It’s) fortuitous timing with this site, the best site in Redcliffe, and the acceptance from the market for apartment living … it all fell into place,” Sam says.

“We couldn’t pass it up.”